Question: Budgeted variable overhead for the year is $150,000. Expected activity is 30,000 standard direct labor hours. The actual hours worked were 15,000 and the standard
Budgeted variable overhead for the year is $150,000. Expected activity is 30,000 standard direct labor hours. The actual hours worked were 15,000 and the standard hours allowed for actual production were 18,000. The variable overhead efficiency variance is:
a.$14,600 F.
b.$30,000 F.
c.$18,000 F.
d.$15,000 F.
e.None of these choices are correct.