Buenaflor Industries Research and Development Department is tasked to come up with an oral anti-viral pill. Presented
Question:
Buenaflor Industries Research and Development Department is tasked to come up with an oral anti-viral pill. Presented below are the list of activities, precedence relations, and duration for the project.
Draw the appropriate AON PERT diagram.
What is the critical path? Encode your answer in this manner: ABCD. *
What is the total project completion time? Encode your answer in this manner: 2 DAYS. *
What is the early finish of activity D? Encode your answer in this manner: 2 DAYS. *
What is the early finish of activity H? Encode your answer in this manner: 2 DAYS.
What is the late start of activity C? Encode your answer in this manner: 2 DAYS.
What is the late start of activity I? Encode your answer in this manner: 2 DAYS.
Compute for the slack time of activity F? Encode your answer in this manner: 2 DAYS.