Question: Build a Gantt chart based on the table shown in the Figure below. Enter the tasks, dependencies, and durations. The Figure presents a list of

Build a Gantt chart based on the table shown in

Build a Gantt chart based on the table shown in the Figure below. Enter the tasks, dependencies, and durations. The Figure presents a list of tasks for a student who wants to have an international experience by attending a university abroad. Assume that all predecessor tasks must finish before the succeeding task can begin (the simplest version). Also, insert a few overview tasks, such as Application tasks, Preparation tasks, Travel tasks, and Arrival tasks. Be sure to state your assumption. Task Id Duration (days) Predecessor task 1 1 None 2 3 1 3 21 2 4 3 2 5 30 4 6 5 3,5 Description Obtain forms from the international exchange office. Fill out and send in the foreign university application. Receive approval from the foreign university, Apply for the scholarship. Receive notice of approval for the scholarship. Arrange financing Arrange for housing in a dormitory. Obtain a passport and the required visa. Send preregistration forms to the university. Make travel arrangements. Determine clothing requirements and go shopping. Pack and make final arrangements to leave. Travel. 7 25 6 8 35 6 9 2 8 10 1 7,9 11 10 10 12 3 11 13 1 12 14 Move into the dormitory. 1 13 15 2 14 Finalize registration for classes and other university paperwork. 16 Begin classes. 1 15 1

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!