Question: Building a swimming pool Task Worker Category Excavate Machine Operator Frame the walls Masons Install Internal Plumbing Plumber Install Electricity Electrician Pour concrete Masons Install
Building a swimming pool
Task Worker Category
Excavate
Machine Operator
Frame the walls
Masons
Install Internal Plumbing Plumber
Install Electricity
Electrician
Pour concrete
Masons
Install pump and filter Plumber
Person # of Elapsed Materials
Days Workers Time (days) ($)
6
2
0 1,500.00
8
4
0 800.00
4
2
0 700.00
2
2
0 500.00
4
2
4 2,000.00
1
1
0 3,000.00
Total 8,500.00
Category
Electrician
Mason
Machine Operator
Plumber
Wage Rate $/Day
200.00
160.00
120.00
200.00
a) Create a Gantt chart from the work breakdown structure.
b) Create a PERT/CPM network showing the interdependencies of the
different activities. How long will the project take? (Note:
Dont forget
to take elapsed time into account.)
c) Using the information in your Gantt chart, as well as the information on
wage rates and cost of materials, put together a budget showing
planned total expenditures for the project.