Question: BUS 530 R. Gunther HOMEWORK PROBLEMS Set #2 Project and Capacity Management 1. Consider the following activity analysis for a project: Activity Description Follows Time

BUS 530 R. Gunther HOMEWORK PROBLEMS Set #2
BUS 530 R. Gunther HOMEWORK PROBLEMS Set #2 Project and Capacity Management 1. Consider the following activity analysis for a project: Activity Description Follows Time (Days A B D E F G H Define Problem Lease Computer Obtain Data Determine Alternatives Feasible Alternatives Evaluation/Model Building Find Best Alternative Implementation A,B A,B D CE F G 3 5 4 1 1 5 1 a. Draw an activity-on-node diagram and find the critical path. b. Find total slack (TS) for each activity