Question: BUSM3630 Project Cost, Quality, Risk, Procurement In this assignment you will submit a status report by examining a scenario and demonstrating understanding of the concepts.
BUSM3630 Project Cost, Quality, Risk, Procurement
In this assignment you will submit a status report by examining a scenario and demonstrating understanding of the concepts. You will apply your learning and provide expert advice to a company in resolving a project management issue. You will analyze costs and risks, demonstrate your understanding of monitoring and controlling project activities and providing appropriate recommendations.
In grading your assignment the instructor will look for evidence that you have kept up with the required reading and can think critically about the concepts discussed. You can include any additional resources and provide appropriate APA style referencing. Your paper should be set up in a business report format.
Your paper should include:
- Title page
- Executive Summary
- Introduction
- Analysis
- Advice and action (Your opinion as an expert).
- Conclusion
- References
Extreme Safe Company (10%)
You are a new project manager who joined the company Extreme Safe twelve months ago. You have a reputation as an effective project manager because your first project management responsibility - reviewing the companys different methods used for estimating project schedule, costs and resources were very successful and senior management were impress with the outcome of the project. Your most recent project is to review two-current projects by interpreting the following project status reports from the company Extreme Safe and provide guidance to the project sponsors on:
- Explain the importance of status reporting
- How to proceed with each project, and
- Justify which of the projects should be given the highest priority for use of shared resources as you can only afford to spend an additional $100,000 on one of the projects. You must choose only one project to support. You may not split the $100,000 between the projects.
Safe Ways: Project 1 Status Report May 2nd
Project Summary
Project 1, will produce a prototype model of a safety cage for prisoner transport that can be easily fitted to many models of vehicle, - the proposed product name is Safe Ways. This potential product was requested by the marketing department to meet a market need in private contractor prisoner transportation for the North American market. The marketing department believe the potential of this product for the company is in the region of $50 million profit annually if it can be produced at a cost of $1,000 and sold for $1,500 (a price point marketing believe represents the sweet spot for the market segment they have identified).
Project Deliverables and Milestones
Project Specifications (Marketing Department product requirements) January 10
High Level Design (Engineering) February 15
1st Pass Model (Project Team) March 15
Field Test 1 April 1
2nd Pass Model (Project Team) April 15
Field Test 2 May 1
3rd Pass Model (Project Team) May 15
Field Test 3 June 1
Project Review and Closure June 15
Major Issues and their impact
Issue 1: Marketing were two weeks late with the project specifications, which the engineering department argued were too vague. After three weeks of back and forth between engineering and marketing a workable specification was agreed.
SPI: 0.9
CPI: 1.1
ETC: $750,000
Change Requests
Accepted: None to date
Open: Request to increase the project budget by $95,000 to compensate for the time lost to marketing and engineering issues.
Risks
Risk One: Engineering are concerned that the large variation in sizes across vehicles models used may negatively impact the possibility of developing an appropriate product. We have started the process of exploring the most used vehicle models for prisoner transportation to reduce the possibility of the product failing (this work will cost $5,000). Marketing have said if we do this we may reduce the potential market for the product by 10%
Safe_n_Sound: Project 2 Status Report May 2nd
Project Summary
Project 2 will produce an update model of our best-selling Safe_n_Sound in house safe room product. This update model was requested by the marketing department to meet a market need for enhanced security and increased comfort and to allow us to hold and grow our market share as competitors launch their latest high comfortable safe room models.
The marketing department believe the potential for the updated model of this product for the company is in the region of $40 million profit annually if it can be produced at a cost of $30,000 and sold for $45,000 (a price point marketing has said our competitors cannot compete against). Should we delay and not update the model they believe we are likely to lose $10, 000 profit annually until our product is no longer a viable product for the market place within four years.
The budgeted cost for the project is $1,000,000
Project Deliverables and milestones
Project Specifications (Marketing Department product requirements) March 10
High Level Design (Engineering) April 1
1st Pass Model (Project Team) April 15
Field Test 1 May 1
2nd Pass Model (Project Team) May 15
Field Test 2 June 1
Project Review and Closure June 15
Major Issues and their impact
None to date
SPI: 1.01
CPI: 0.9
ETC: $720,000
Change Requests
Accepted: None to date
Open: Request to reduce the project deadline by two weeks to allow for launch at a new trade show in Las Vegas, allowing for a bump in advance sales and taking market share from our competitors. This change request will cost us an additional $100,000 in project costs.
Risks
Risk One: Reduce the project deadline by two weeks to allow for launch at a new trade show in Las Vegas, allowing for a bump in advance sales and taking market share from our competitors in the region of $1,000,000.
Response: Hire additional personnel for development and trade show launch at a cost of an additional $100,000 to the project needs management approval.