Question: By the time midterms come around, you have completed zero (0)% of your project management class under the 0/100 rule. True False Use the S-curve

By the time midterms come around, you have completed zero (0)% of your project management class under the "0/100 rule". True False Use the S-curve to choose the best statement about the project it describes. The horizontal axis is in weeks. The actual week number is the midpoint of the column. The total project costs in week 10 are less than budgeted. The total project costs in week 10 exceed the budgeted cost. The project cost more from weeks 25 through 30 than it did in weeks 10 through 15. The total amount spent on the project at the end of the 20 th week is approximately $30,000
Step by Step Solution
There are 3 Steps involved in it