Question: c) Compute the net quantities needed if there are 25 of the base and 75 of the clamp in stock. Base: Spring: Clamp: Housing:


c) Compute the net quantities needed if there are 25 of the base and 75 of the clamp in stock. Base: Spring: Clamp: Housing: Handle: Casting: Bearing: Shaft: units (enter your response as a whole number). units (enter your response as a whole number). units (enter your response as a whole number). units (enter your response as a whole number). units (enter your response as a whole number). units (enter your response as a whole number). units (enter your response as a whole number). units (enter your response as a whole number). Get more help Clear all Check answer As the production planner for Xiangling Hu Products, Inc., you have been given a bill of material for a bracket that is made up of a base, 1 spring, and 3 clamps. The base is assembled from 2 clamps and 1 housing. Each clamp has 1 handle and 2 castings. Each housing has 1 bearing and 2 shafts. There is no inventory on hand. a) Design a product structure noting the quantities for each item and show the low-level coding. Match each number in the structure below with the corresponding item. Number Item | Spring(1) || Housing (1) III IV Casting (2) Shaft (2) Clamp (2) Bracket I Base (1) Clamp(3) Handle (1) III Bearing (1) IV Handle (1) Casting(2) b) Determine the gross quantities needed of each item if you are to assemble 50 brackets.
Step by Step Solution
There are 3 Steps involved in it
To compute the net quantities needed for a production run of 50 brackets when there are 25 bases and ... View full answer
Get step-by-step solutions from verified subject matter experts