Question: c . Consider the original data ( overtime per employee per month 2 0 hours and 1 , 2 5 0 workers ) for the

c. Consider the original data (overtime per employee per month 20 hours and 1,250 workers) for the case in which Skycell aims for a level production schedule such that the quantity produced each month does not exceed the average demand over the next 12 months (1,241,667) by 50,000 units. Thus, monthly production, including overtime, should be no more than 1,291,667. What would be the cost of this level production schedule?