Question: C, D W E Pour foundation 7. The project information for the custom order project of the Air Control Company is presented here. Draw a

C, D W E Pour foundation 7. The project information for the custom order project of the Air Control Company is presented here. Draw a project network Page 198 for this project. Compute the early and late activity times and slack times. Identify the critical path. ID Description Predecessor Time None 2 A Order review B Order standard parts A 3 C Produce standard parts A 10 D Design custom parts A 13 E Software development A 18 F Manufacture custom hardware C, D 15 G Assemble B. F 10 H Test E, G 5 8. You have signed a contract to build a garage for the Simpsons. You will receive a $500 bonus for completing the project within 17 working days. The contract also contains a penalty clause in which you will lose $100 for each day the project takes longer than 17