Question: c ) Kayabars Sdn . Bhd . is a manufacturer of Front Car Absorbers for Proton S 7 0 . The company has secured 1

c) Kayabars Sdn. Bhd. is a manufacturer of Front Car Absorbers for Proton S70. The company has secured 10 years of contract to supply the absorbers. The absorber is made up one (1) unit each of Knuckle, Struts and Strut Mount assemblies.
The Knuckle assembly comprises one (1) unit of Lower Control Arm, one (1) unit of Steering Link. The Lower Control Arm is attached to the Knuckle using one (1) unit of Bolt and one (1) unit of Nut. Then, the Steering Link is tightened to the Knuckle assembly using three (3) units of Bolt and three (3) units of Nut.
The Struts assembly comprises one (1) unit of Lower Spring Insulator, one (1) unit of Upper Spring Insulator and one (1) unit of Spring Set. One (1) unit of Jounce Bumper is jointed to Spring Set using a snap fit method.
Struts Mount Assembly is assembled using one (1) unit Strut Mount Housing and is tightened using five (5) units of Nut.
Front Car Absorbers will be delivered to the customer in week 40. The lead time and onhand inventory information are given in Table 1.3.
4-
SEMM3813
Table 1.3: Lead time and on-hand inventory data
\table[[Item,\table[[Lead time],[(week)]],\table[[On-hand],[inventory (Unit)]]],[Front Car Absorber,1,10],[Knuckle
\table[[Lower Arm],[Steering Link],[Bolt]],1,5],[Nut,2,7],[,1,7],[Strut,2,30],[Lower Spring Insulator,2,30],[Upper Spring Insulator,2,10],[Spring set,1,10],[Jounce Bumper,1,20],[Strut Mount,2,7],[Strut Mount Housing,1,8],[Nut,1,5],[,,5]]
i. Design a product structure for the front car absorber unit based on low-level coding. (2 marks)
ii. Construct a time-phased product structure for the front car absorber unit.
(2 marks)
iii. Determine the quantity of Bolt and Lower Spring Insulator that should be ordered to deliver 100 units of front car absorber in week 40. Develop a net material requirement plan using the table provided in Appendix I. The ordering of items is based on lot-for-lot policy.
(6 marks)
c ) Kayabars Sdn . Bhd . is a manufacturer of

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!