The table below gives the predecessor activities, as well as the optimistic, most likely, and pessimistic times, for the activities of a project.
\table[[Activity,Predecessor,Optimistic,Likely,Pessimistic],[A,-,4,6,10],[B,A,2,5,8],[C,A,6,7,9],[D,B,3,9,20],[E,C,7,9,11],[F,D,E,7,11,19]]
Given this information, the probability that the project will be completed by the 28 th day