Question: [C] Starting with the duration corresponding to minimum cost calculated in part [A] as the normal duration, the subcontractor is examining reducing the execution duration.

 [C] Starting with the duration corresponding to minimum cost calculated in

part [A] as the normal duration, the subcontractor is examining reducing the

[C] Starting with the duration corresponding to minimum cost calculated in part [A] as the normal duration, the subcontractor is examining reducing the execution duration. He decides to pay extra money to reduce the task's duration such that cost per crashed day should not exceed L.E. 500. Determine the execution plan's satisfying his condition