Question: c . The critical activities are A , C , E , and G so they make up the critical path. Part 9 The entire

c. The critical activities are
A, C, E, and G
so they make up the critical path.
Part 9
The entire project will take
22 days to complete. (Enter your response rounded to one decimal place.)
Part 10
d. Management would like to complete the project in less than 16 days. Management has determined that activity Upper E can be crashed 0.5days, for a total cost of $15 comma 000. No other activities can be crashed.
After crashing,
is the critical path. The entire project will take
enter your response here days. (Enter your response rounded to one decimal place.)