Question: C) The project length for the leadership training program development project = ______ days. D) Slack Time for each of the activities is: A-G Roger
C) The project length for the leadership training program development project = ______ days.
D) Slack Time for each of the activities is: A-G
Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors, and times appear in the accompanying table: Activity Immediate Predecessor(s) Time (days) B C 6 1 10 5 5 8 B AD E, F E F G This exercise contains only parts b, c, and d. b) The critical activities for the leadership training program development project are