Question: c. What is the expected project completion time? (Do not round intermediate calculations. Round your answer to 3 decimal places.) d. What is the probability

c. What is the expected project completion time? (Do not round intermediate calculations. Round your answer to 3 decimal places.) d. What is the probability of completing this project within 23 days? (Use Excel's NORM.S.DIST() function to find the correct probability for your computed Z-value. Do not round intermediate calculations. Round "z" value to 2 decimal places and final answer to 4 decimal places.)
The following represents a project that should be scheduled using CPM: IMMEDIATE TIMES (DAYS) ACTIVITY PREDECESSORS am b 1 4 1 6 11 2 6 7 3 2 13 B 1 2 6 1 59 D, E 1 2 F,G 36 IOTM0OUD III C,D b. What is the critical path? B-E-G-H O A-C-F-H O A-D-F-H A-D-G-HStep by Step Solution