Question: C&A Fast Food has four activities in serving a customer: greet customer, take order, process order, and deliver order. Each activity is staffed by one

C&A Fast Food has four activities in serving a customer: greet customer, take order, process order, and deliver order. Each activity is staffed by one employee (for a total of four employees). The processing time for each activity is given as follows:
Activity Processing time per customer
Greet customer 2 seconds
Take order 30 seconds
Process order 60 seconds
Deliver order 5 seconds
Assume demand is unlimited. To which activity should C&A assign an additional employee in order to increase process capacity?
Multiple Choice
Greet customer
Take order
Process order
Deliver order

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!