Question: C&A uses a two-step process to make a part. The first step involves cutting with a machine that requires a 40-minute setup time before the

C&A uses a two-step process to make a part. The first step involves cutting with a machine that requires a 40-minute setup time before the production of each batch. The cutting takes 30 minutes per part. The second step is polishing the parts from cutting. The polishing takes 40 minutes per part. Assume batch size is 2 parts. What is the process capacity (parts/minute) ? There is NO inventory buffer in the process.

1/60

1/50

1/40

Cannot be determined .

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!