CAC operates 3 eight hour shifts to produce 600 gallons of chemicals per day. It requires 12
Fantastic news! We've Found the answer you've been seeking!
Question:
CAC operates 3 eight hour shifts to produce 600 gallons of chemicals per day. It requires 12 minutes of labor to produce a gallon of the chemical . What is CAC's Takt time in minutes per gallon ? What is the Target manpower ? Show all formulas, calculations and results.
Posted Date: