Question: Calculate 2nd part only 1. In the process below, as shown, 75% of the arrival rate goes through step 2 and 4, and the rest


Calculate 2nd part only
1. In the process below, as shown, 75% of the arrival rate goes through step 2 and 4, and the rest of them go through step 3. Determine the value of T: (Duration or average Flow Time of step 1), 12 (Average Inventory for Step 2), and T3 (Average Flow Time of step 3). Do not forget to convert the units if needed for dimensions to match, before using a parameter value in the formula (6 points). Consider each month to be 30 days if needed. Step 2 T2-2 days Step 4 14 120 75% R1-1,000 applications per month End Start Step 1 11- 200 Step 3 13-100 = Arrival rate = 75% given) To find out T1, 12, T3 2. Identify the critical path in problem 1, and show your calculations through which you concluded on the chosen path (4 points). ncont of "Production Mix Modification" strategy by using the following data, which show the time Aduction is the Sol : disume I month : 30 days So, T2 = 2 - 2 days 2 30 = 0.0667 months. flow late in Step applications per month Flow time in months (T) WIP (1) 200 1 1000 0.2 200 1000 2 600 0.067 600 0.067 SHO 100 3 H00 0.25 H00 100 120 4 600 0.20 120 600 So, Ti = 0.2 months til. = 6days 72 = 40 T3 = 0.95 months Tis daysStep by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock