Question: Calculate a Level 3 efficiency variance for materials given the following information: budgeted units produced: 5 0 0 budgeted material used in kgs: 7 0

Calculate a Level 3 "efficiency" variance for materials given the following information:
budgeted units produced: 500
budgeted material used in kgs: 700
budgeted total material cost: $9100
actual units produced: 700
actual kgs used: 1050
actual total material cost: $10500
$880U
$910U
$910F
none of the listed answers are correct
$880F
 Calculate a Level 3 "efficiency" variance for materials given the following