Question: Calculate earned value for each activity, and for the project. Calculate project efficiency for the overall project as well as each activity at this stage
Calculate earned value for each activity, and for the project. Calculate project efficiency for the overall project as well as each activity at this stage based on dollars.
Activity Budgeted Actual % complete Pay rate
Analysis & design 5 weeks 6 weeks 100% $7000/week
Production 10 weeks 8 weeks 70% $12000/week
Testing 4 weeks 2 weeks 50% $3000/week
Installation 2 weeks 0 0 $2000/week
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
