Question: Calculate earned value for each activity, and for the project. Calculate project efficiency for the overall project as well as each activity at this stage

Calculate earned value for each activity, and for the project. Calculate project efficiency for the overall project as well as each activity at this stage based on dollars.

Activity Budgeted Actual % complete Pay rate

Analysis & design 5 weeks 6 weeks 100% $7000/week

Production 10 weeks 8 weeks 70% $12000/week

Testing 4 weeks 2 weeks 50% $3000/week

Installation 2 weeks 0 0 $2000/week