Question: Calculate the critical path length (by creating network diagram) for the project activities given in the table. What is the duration of the project? Write

Calculate the critical path length (by creating network diagram) for the project activities given in the table.


What is the duration of the project?


Write the critical path?


What are the activities that can be delayed without affecting the schedule time of the project.


Number

Activity

Predecessor

Duration

1

Design house and obtain financing

--

3 months

2

Lay foundation

1

2 months

3

Order and receive materials

2

2 month

4

Build house

2,3

3 months

5

Select paint

3

2 month

6

Select carper

5

3 month


Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!