Question: Calculate the direct labor quantity variance from the information given below. Standard rate $13 per hour Standard hours 4,300 hours Actual hours 5,000 hours Actual
Calculate the direct labor quantity variance from the information given below.
| Standard rate | $13 per hour |
| Standard hours | 4,300 hours |
| Actual hours | 5,000 hours |
| Actual rate | $11.50 per hour |

$9,100 unfavorable

$15,550 unfavorable

$6,450 unfavorable

$1,600 favorable
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts