Question: Calculate the expected completion time for activity G. Activity Time Estimates Predecessors a m b A 2 4 7 _ B 2 6 7 A
Calculate the expected completion time for activity G.
| Activity | Time Estimates | Predecessors | ||
| a | m | b | ||
| A | 2 | 4 | 7 | _ |
| B | 2 | 6 | 7 | A , D |
| C | 3 | 4 | 6 | D |
| D | 6 | 12 | 12 | A |
| E | 3 | 6 | 12 | D |
| F | 6 | 8 | 16 | B , C |
| G | 2 | 8 | 9 | E , F |