Question: Calculate the following and create a PERT Analysis Number Activity Predecessor Best-Case Likely Worst-Case Duration Var 1 Assign Project Manager Start 2 Define Project Goals
Calculate the following and create a PERT Analysis
| Number | Activity | Predecessor | Best-Case | Likely | Worst-Case | Duration | Var |
| 1 | Assign Project Manager | Start |
|
|
|
|
|
| 2 | Define Project Goals and Objectives | 1 |
|
|
|
|
|
| 3 | Retrieve Client Approval and Determine Business Need | 1 |
|
|
|
|
|
| 4 | Needs Analysis and Define Scope | 2 |
|
|
|
|
|
| 5 | Create Project Plan and Budget | 2 |
|
|
|
|
|
| 6 | Define Roles and Responsibilities | 3 |
|
|
|
|
|
| 7 | Process Improvements | 3 |
|
|
|
|
|
| 8 | Establish Team Expectations | 4, 5 |
|
|
|
|
|
| 9 | Plan roll-out and Pilot | 4, 5 |
|
|
|
|
|
| 10 | Document Lessons Learned | 5, 6 |
|
|
|
|
|