Question: Calculate the internal rate of return on investment (IRR), levelized cost of electricity (LCOE), and net present value (NPV) for the following generic power plant:

 Calculate the internal rate of return on investment (IRR), levelized cost

Calculate the internal rate of return on investment (IRR), levelized cost of electricity (LCOE), and net present value (NPV) for the following generic power plant: A power plant generates a design maximum of 5 MW of electricity The power plant takes one year to build (year 0.) The total installed cost of the plant is $2500/kw. The lifetime of the power plant after construction is assumed to be 20 yrs. (1-20) The power plant has a capacity factor of 80% in the first year of operation after construction, 85% in the second year of operation, and 90% in years 3 through 20. The capacity factor tells you what percentage of the year the power plant is operating at its design rated maximum power. Assume that fixed+variable O&M costs are 7%/yr of the $2500/kW upfront installed capital cost, i.e. that O&M fixed+variable costs are $175/kW per year. Assume that, after the 20 years of operation, you must decommission the power plant. The decommissioning takes place over 1 year. The total cost of decommissioning the plant is $500/kW (i.e. $2.5M in year 21.) Assume that the sale price of electricity is $50/MWh (for NPV and IRR) and that the discount rate is 7%/yr (LCOE and NPV) Assume that there is no inflation in O&M costs or sale price of electricity. Use the equations below {or =IRR(cells, guess) in Excel). Answers should be in units of [% / yr], [$/MWh), and [$] . . Calculate the internal rate of return on investment (IRR), levelized cost of electricity (LCOE), and net present value (NPV) for the following generic power plant: A power plant generates a design maximum of 5 MW of electricity The power plant takes one year to build (year 0.) The total installed cost of the plant is $2500/kw. The lifetime of the power plant after construction is assumed to be 20 yrs. (1-20) The power plant has a capacity factor of 80% in the first year of operation after construction, 85% in the second year of operation, and 90% in years 3 through 20. The capacity factor tells you what percentage of the year the power plant is operating at its design rated maximum power. Assume that fixed+variable O&M costs are 7%/yr of the $2500/kW upfront installed capital cost, i.e. that O&M fixed+variable costs are $175/kW per year. Assume that, after the 20 years of operation, you must decommission the power plant. The decommissioning takes place over 1 year. The total cost of decommissioning the plant is $500/kW (i.e. $2.5M in year 21.) Assume that the sale price of electricity is $50/MWh (for NPV and IRR) and that the discount rate is 7%/yr (LCOE and NPV) Assume that there is no inflation in O&M costs or sale price of electricity. Use the equations below {or =IRR(cells, guess) in Excel). Answers should be in units of [% / yr], [$/MWh), and [$]

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!