Question: Calculate the labour efficiency variance and indicate whether the variance is favourable or unfavourable. ( 4 marks ) INFORMATION The standard time and labour cost

Calculate the labour efficiency variance and indicate whether the variance is favourable or unfavourable. (4 marks) INFORMATION The standard time and labour cost of Strava Manufacturers for each unit of Product X is 3.5 hours at R40 per hour. The expected monthly production is 4500 units. The actual figures for May 2025 are as follows: Production 4000 units Direct labour incurred 15000 hours at R39 per hour