Question: Calculate the MPS and ATP using the following data. Demand time fence = 2 Planning time fence = 7 Safety stock = 5 Lot size
Calculate the MPS and ATP using the following data.
Demand time fence = 2
Planning time fence = 7
Safety stock = 5
Lot size = 30
| Period | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 |
| Forecast Sales | 20 | 20 | 20 | 20 | 20 | 20 | 20 | 20 | 20 |
| Customer Order | 18 | 15 | 27 | 10 | 10 | 8 | 6 | 5 | 5 |
| PAB = 20 | |||||||||
| ATP | |||||||||
| MPS |