Question: Calculate the Net Present Worth (or Net Present Value), and benefit-cost (B/C) ratio of the following project, assuming an 8% discount rate. Also determine the
Calculate the Net Present Worth (or Net Present Value), and benefit-cost (B/C) ratio of the following project, assuming an 8% discount rate. Also determine the projects Internal Rate of Return (IRR).
| Year | Cash Flow ($) |
| 0 | -400.00 |
| 5 | -100.00 |
| 15 | +500.00 |
| 30 | +2,500.00 |