Question: Calculate the Overall Equipment Effectiveness ( OEE ) for a process with the following performance metrics: Uptime of 7 hours out of an available 8

Calculate the Overall Equipment Effectiveness (OEE) for a process with the following performance metrics:
Uptime of 7 hours out of an available 8 hours
200 units produced during those 7 hours
Designed hourly production rate of 32 parts per hour
12 scrapped parts out of the 200 produced
94%
79%
64%
73%
88%