Question: Calculate the project cash flow generated for Project A and Project B using the NPV method (Show your calculations): . Project A: Invest $10k today
Calculate the project cash flow generated for Project A and Project B using the NPV method (Show your calculations): . Project A: Invest $10k today and receive $5k at the end of this year and for another 2 years (in 12 mos, in 24 mos, in 36 mos), for total cash inflows of $15k. Project B: Invest $55k today and receive $20k at the end of this year and for another 2 years (in 12 mos, in 24 mos, in 36 mos), for total cash inflows of $60k.
Discount rate = 10%