Question: Calculate the project cost & duration after crashing process Activity Precedence a Duration, Days (norm/crash) 3,2 2,1 2,2 4,1 3,1 Slope ($/day) 40/ - 1

Calculate the project cost & duration after crashing process
Activity Precedence a Duration, Days (norm/crash) 3,2 2,1 2,2 4,1 3,1 Slope ($/day) 40/ - 1 = - 40 60/- 1 = - 60 a b d Cost (norm/crash) $ 40, 80 20,80 20, 20 30, 120 10,80 a a b 90/ - 3 = - 30 - 70 (2 days) *Partial crashing allowed **Partial crashing not allowed