Question: calculate the slack for each activity Immediate Predecessor(s) Activity A Activity Time (days) 7 1 5 5 4 D A . B, C D E

calculate the slack for each activity

calculate the slack for each activity Immediate

Immediate Predecessor(s) Activity A Activity Time (days) 7 1 5 5 4 D A . B, C D E E 6 5 G a. Choose the correct network diagram for this project. O A. . o 3 Start 2 Finish Start Finish OC. M. 6 Start Finish Start Finish 6 b. Determine the critical path and project duration The critical path is path A-C-D-E-F and the project duration is 27 days. (Enter your response as an integer.) c. Calculate the slack for each activity. (Enter your responses as integers.) Slack (days) Activity A B TOO D