Question: Calculate the time estimate for a task with the following values: Optimistic 2 0 days, Realistic 4 0 days, and Pessimistic 8 0 days

Calculate the time estimate for a task with the following values: Optimistic 20 days, Realistic 40 days, and Pessimistic 80 days