Question: Calculating X from a Known Probability Although they have a contingency plan for management to operate the machinery if a strike should occur, they only

Calculating X from a Known Probability

Although they have a contingency plan for management to operate the machinery if a strike should occur, they only have enough people trained to cover 8% capacity of the normal distribution.

The average number of pots produced each day at the processing plant is 30,000 with a standard deviation of 3,200. (Assuming a normal distribution)

How many pots would be produced per day under these circumstances? (show work)