Question: Calculation Problem (6 points each) 1. The following operation works 8 hours per day. Compute the maximum and minimum possible output rate per day
Calculation Problem (6 points each) 1. The following operation works 8 hours per day. Compute the maximum and minimum possible output rate per day for this operation. Process Processing Time Preceding Activity 1 60 sec per unit 2 10 sec per unit 1 3 50 sec per unit 2