Question: Calculation (using Excel or other spreadsheet software is recommended) The raw materials manager at your company asks you to design a Single-Sampling Plan with n=150

 Calculation (using Excel or other spreadsheet software is recommended) The raw

Calculation (using Excel or other spreadsheet software is recommended) The raw materials manager at your company asks you to design a Single-Sampling Plan with n=150 and c=2 for receiving inspection. The supplier ships the product in lots of size N=3,000. a. Draw the OC curve for this plan. b. Draw the AOQ curve and find the AOQL. c. Draw the ATI curve for this plan