Question: Callers are helped in a process with two resources. The first resource has a capacity of 1 callers per minute. The capacity of the second

Callers are helped in a process with two resources. The first resource has a capacity of 1 callers per minute. The capacity of the second resource is 1.4 callers per minute. The first resource has 2 workers and the second resource has 4 workers. What is the labor content (in minutes)? Note: Do not round intermediate calculations. Round your answer to 2 decimal places