Question: Cameron Circuits is scheduling their orders using the following information. Today is day 100 - Order 10: Due on day 120, 10 days of lead
Cameron Circuits is scheduling their orders using the following information. Today is day 100 - Order 10: Due on day 120, 10 days of lead time remain to complete the order - Order 20: Due on day 130,10 days of lead time remain to complete the order - Order 30: Due on day 110,4 days of lead time remain to complete the order - Order 40: Due on day 125, 8 days of lead time remain to complete the order Which sequence should they follow if they use the Critical Ratio priority rule? Order 40, Order 20 , Order 30 , Order 10 Order 30 , Order 40 , Order 10 , Order 20 Order 20 , Order 40 , Order 30 , Order 10 Order 10 , Order 30 , Order 20 , Order 40