Question: CAMMIMS 1 6 9 . E . 0 1 8 . ASK YOUR TEACHER You may need to use the appropriate technology to answer this

CAMMIMS169.E.018.
ASK YOUR TEACHER
You may need to use the appropriate technology to answer this question.
Due to population growth in the area, the new Liberty High School has just opened in a local school district. The athletic director at Liberty High is planning the launch of the school's track and field team. The first team practice is scheduled for April 1. The activities, their immediate predecessors, and the activity time estimates (in weeks) are listed in the following table.
\table[[Activity,Description,\table[[Immediate],[Predecessor]],Optimistic,Most Probable,Pessimistic],[A,Meet with board,,1,1,2],[B,Hire coaches,A,4,6,8],[C,Conduct fundraiser,A,2,4,6],[D,Announce program,B, C,1,2,3],[E,Meet with coaches,B,2,3,4],[F,Order team equipment,A,1,2,3],[G,Register athletes,D,1,2,3],[H,Reserve buses for meets,G,1,2,3],[I,Plan first practice,E, H, F,1,1,1]]
(a) Draw a project network.
(1)
(b) Develop an activity schedule. (Round your answers to two decimal places.)
\table[[Activity,\table[[Earliest],[Start]],\table[[Latest],[Start]],\table[[Earliest],[Finish]],\table[[Latest],[Finish]],Slack],[A,,,,,],[B,,,,,],[C,,,,,],[D,,,,,],[E,,,,,],[F,,,,,],[G,,,,,],[H,,,,,],[I,,,,,]]
(c) What are the critical activities? (Enter your answers as a comma-separated list.)
What is the expected project completion time (in weeks)?(Round your answer to two decimal places.) weeks
(d) If the athletic director plans to start the project on January 1, calculate the probability the track and field team will be ready by the scheduled April 1 date (13 weeks) based solely on the critical path. (Round your answer to four decimal places.)
Should the athletic director begin planning the track and field team before January 1?(The probability for finishing on schedule should be at least 0.9.)
Since the probability that the track and field team will be ready by April 1 is ---Select-- hat(v) than 0.9, the athletic director ---Select-- diamond begin planning before January 1.
Need Help?
 CAMMIMS169.E.018. ASK YOUR TEACHER You may need to use the appropriate

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!