Question: Can I have a help how to solve for its project network? Because when I did, it would not get the same answer for slack
Can I have a help how to solve for its project network? Because when I did, it would not get the same answer for slack in the activity G.
My assignment is about Project Scheduling in my subject, Management Science.
Activity Description Immediate Predecessor Time (weeks) A Survey building site None 6 B Develop initial design None 8 C Obtain board approval A, B 12 D Select architect C 4 E Establish budget C 6 F Finalize design D, E 15 G Obtain financing E 12 H Hire contractor F. G 8
Requirement 1: Draw a project network (with the compartments)
Requirement 2: Identify the critical path.
Requirement 3: Develop the activity schedule for the project.
Requirement 4: Does it appear reasonable that construction of the athletic complex could begin one year after the decision to begin the project with the site survey and initial design plans? What is the expected completion time for the project?
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
