Question: can i have help with this question question 12 This Test: 39 pts possible Submit Test Predecessor -- A Activity A B D E F

can i have help with this question
question 12
can i have help with this question question 12
can i have help with this question question 12
This Test: 39 pts possible Submit Test Predecessor -- A Activity A B D E F G 000 Time(weeks) 8 6 4 9 11 3 1 A B D.E.F. OPS 1100 Test: E-Test3 Question 11 What is the minimum number of activities that would have to be delayed to cause an increase in the project's earliest completion date? O A Four or more activities OB. One activity C. Two activities O D. Three activities D