Question: can someone answer please 2. Halima & Co has just been awarded a contract by Exxon Mobil. The Job requires 30 kgs of a material
2. Halima & Co has just been awarded a contract by Exxon Mobil. The Job requires 30 kgs of a material which cost $16 per kg, as well as 1kg of a special component that can be bought at a cost of $140 per kg. 20 hours labour were spent on the job and the employees were paid at $8 per hour. In addition, 5 hours was spent by a supervisor who was paid at $14 per hour. Overheads are absorbed at the rate of $5 per labour hour. Required: Calculate the total absorption cost of the job