Question: can someone explain clearly how this answer comes out. I will give a thumb up. 1. A project consisting of eight activities satisfies the following
can someone explain clearly how this answer comes out. I will give a thumb up.
1. A project consisting of eight activities satisfies the following precedence constraints: (a) Construct a network for this project. (You should need only one pseudo activity) (b) Compute the earliest and the latest starting and finishing times for each activity and identify the critical path. Solution to Assignment 8 (a) (b) ABDFG