Question: Can someone help me with the below? . Define the following: TBC, CBC, CAC, CEV, CPI, CV, and FCAC. What formulas are used to calculate

Can someone help me with the below?

Can someone help me with the below? . Define the

. Define the following: TBC, CBC, CAC, CEV, CPI, CV, and FCAC. What formulas are used to calculate CEV, CPI, CV, and FCAC (3 methods for FCAC)? Assume you are the project manager and based on your customer's requirements you have determined there are four main tasks in a Dream Backyard project and have assigned each a TBC. Specifically, the customer wants the backyard leveled (Task 1 - $15,000); wants a covered outdoor kitchen with a hot tub and firepit (Task 2 - $20,000), a retaining wall with fencing built- in (Task 3 - $25,000), and a pool with waterfall (Task 4 - $60,000). You estimate this will take 5 weeks to complete. The costs are budgeted as follows: Budgeted Per Week (in 000's) TBC 1 2 3 4 5 Task 1 15 6 6 3 Task 2 20 2 3 10 4 1 Task 3 25 7 8 6 4 Task 4 60 10 25 20 5 What is the total cumulative TBC? What is TBC at the end of week 4? Assume 4 weeks have passed and these are the actual costs per week: Actual Costs Per Week (in 000's) 1 2 3 4 Task 1 12 3 Task 2 4 7 16 4 Task 3 10 5 6 Task 4 11 17 15 What is the CAC at the end of week 4? Below is the cumulative percentage of work complete per task per week: Cumulative Percentage Complete 1 2 3 4 Task 1 10% 40% 80% 90% Task 2 5% 30% 45% 75% Task 3 50% 80% Task 4 5% 15% 35% 70% What are the CEV, CPI, and CV at the end or week 4? 5

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!