Question: can someone show me the steps to get each answer ? please Question 1 7 pts A future construction project has the following activity relationships
can someone show me the steps to get each answer ? please
Question 1 7 pts A future construction project has the following activity relationships and activity time estimates (in days): Activity Immediate Predecessor To Tm A None 4 5 6 6 ON B None 3 6 ON 21 B 1 c D 1 4 7 A 2 N 5 8 E CD 3 6 15 F 3 9 21 G 2 4 6 H 2 2 EF F, G 2 Leave 2-decimal if not exact, do not round up, for example, 4.3268... will be kept as 4.32 1. Please calculate the expected finish time" and "variance for each activity. What is the expected finish time of activity F? What is the activity variance of activity ? 2. Use "expected finish time of each activity to construct the network. What is the critical path of the project? (no space permitted between letters, acceptable format: ABCD) What is the expected project completion time in days? What is the variance of project completion time? 3. Use "expected finish time to decide ES, EF, LS, LF of each activity. What is the LS time of activity What is the slack time of activity D? E
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock