Question: Can someone teach me the process to answer this type of question please! USING THE FOLLOWING TABLE, DRAW A NETWORK DIAGRAM AND ANSWER THE FOLLOWING:
Can someone teach me the process to answer this type of question please!
- USING THE FOLLOWING TABLE, DRAW A NETWORK DIAGRAM AND ANSWER THE FOLLOWING:
(the diagram is the same for all questions of this type throughout the exam-so only draw it once to answer all the questions)
Given: Activity A - Duration 4 - Predecessor none
Activity - B Duration 6 - Predecessor none
Activity C - Duration 5 - Predecessor A
Activity D - Duration 7 - Predecessor A, B
Activity E - Duration 5 - Predecessor C
Activity F - Duration 7 - Predecessor D
Activity G - Duration 5 - Predecessor D, B
Activity H - Duration 4 - Predecessor B
Activity I Duration 4 Predecessor E.F
Is D on the critical path?
True
False
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts