Question: can you help me complete this Constructing AON and AOA Diagrams Task Predecessors Optimistic Estimate for Duration Most Likely Estimate for Duration Pessimistic Estimate for

can you help me complete this Constructing AON and AOA Diagrams

Task Predecessors Optimistic Estimate for Duration Most Likely Estimate for Duration Pessimistic Estimate for Duration Expected Duration
Start 0 0 0
A Start 6 8 11
B Start 2 6 10
C Start 2 5 9
D A 3 7 14
E A 1 5 8
F C 1 4 9
G C 3 9 14
H B, E, F 5 10 14
I B, D, E, F 6 9 13
J B, E, F, G 8 15 22
End I, J 0 0 0

Consider the following table with activities in a project, predecessors and duration for each activity.

Activity Predecessor Duration in Months
Start 0
A Start 6
B A, E 2
C B 2
D C 3
E Start 1
F A, E 1
G B, F 7
Finish D, G 0

Draw an AON (Activity on Node) diagram for the above project. Indicate the activities in the nodes and also indicate the durations for each activity.

Draw an AOA (Activity on Arrow) diagram for the above project. Indicate the activities in the arrows and also indicate the durations for each activity.

Consider the following table with activities in a project, predecessors and durations for each activity.

Task Predecessors Optimistic Estimate for Duration Most Likely Estimate for Duration Pessimistic Estimate for Duration Expected Duration
Start 0 0 0
A Start 6 8 11
B Start 2 6 10
C Start 2 5 9
D A, B 3 7 14
E B, C 1 5 8
F A, B, C 1 4 9
End E, F 0 0 0

Compute the expected durations for each activity using the three point estimation method.

Draw an AON (Activity on Node) diagram for the above project. Indicate the activities in the nodes and also indicate the durations for each activity.

Draw an AOA (Activity on Arrow) diagram for the above project. Indicate the activities in the arrows and also indicate the durations for each activity.

Consider the following table with activities in a project, predecessors and durations for each activity.

Compute the expected durations for each activity using the three point estimation method.

Draw an AON (Activity on Node) diagram for the above project. Indicate the activities in the nodes and also indicate the durations for each activity.

Draw an AOA (Activity on Arrow) diagram for the above project. Indicate the activities in the arrows and also indicate the durations for each activity.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Databases Questions!