Question: Can you help me finish the doc for Project Management please!! In - class Exercise Question 1 Legend In - class Exercise Question 2 Legend

Can you help me finish the doc for Project Management please!!
In-class Exercise Question 1
Legend
In-class Exercise Question 2
Legend
A three-step process to calculate a schedule with ES, EF, LS, LF
Forward pass: determine ES, EF
Backward pass: determine LS, LF
Calculate float/slack & identify critical path
Float = LS - ES
Use the three-step process below, calculate a schedule with ES, EF, LS, LF dates for project network
|diagram shown in Exercises 1 and 2 in lecture slides (in-class).
Forward pass: determine ES, EF
Backward pass: determine LS, LF
Calculate float/slack & identify critical path
Float =LS - ES
Assumptions
The ES date of the first task is on the first day of the project
Legend
The duration of tasks are counted in days.
The start of a task is assumed to be 8 a.m. and the finish is 5p.m.
The project finish date can be either the EF of the last task or externally imposed date.
Question 1
The critical path is (list tasks on the critical path):
length of the critical path is
Question 2
The critical path is (list tasks on the critical path):
Can you help me finish the doc for Project

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!